This project involved the stripping out, completely of all offices on 1st & 2nd Floor, the creation of a new 1st floor Office Extension into FMC Kongsberg Services Ltd Low Bay Production Workshop and a New Restaurant / Canteen
A Phased Plan was worked to permit FMC to remain operational throughout the Upgrading Works, where the 1st Floor and 1st Floor Extension became Phase 1 & on completion FMC Personnel took temporary occupancy to permit the Ground Floor Offices and New Canteen.
The Ground Floor Offices incorporated a new Corporate Board Room as well as upgrading all Personnel Offices.
The 3rd Phase of the Project was to provide FMC Kongsberg Services Ltd with a New Access Road linking Buildings 1 & 2 together and the addition of much needed Car Parking Spaces.
The Project was completed ahead of Timescale and on Budget.
Project Value - £450K
Project Timescale - 5 Months (incorporating Phases 1, 2 & 3)
![]() |
![]() |
|
| 1st Floor Office Refurbishment, part of Phase 1, Services Upgrade. New CAT 6 cabling introduced within existing service runs under existing raised access floor. | New Demountable Partitioning being formed creating new ground floor layout - Phase II. | |
![]() |
![]() |
![]() |
| Ground Floor Refurbishment highlighting Feature Safety Glazed Partition c/w Company Advertising Manifestation | Ground Floor Refurbishment nearing completion highlighting new demountable partitioning c/w full height glazed screens featuring integral blinds providing privacy, when required. | View from 1st Floor Extension Gallery into existing workshop, prior to occupation. |
![]() |
![]() |
![]() |
| External Works begin creating new access road linking Buildings 1 and 2 and provision of additional car parking. New surface water drainage, french drain and protection of existing fibre optic cable and test station for existing interceptor all formed part of contract. | ||